Flats 1-6
- Painting work on internal communal area has resumed and expected to complete over the next few weeks – COMPLETED
- New stainless-steel balustrades installed in addition to incumbent wooden balustrades – COMPLETED
- Re-paint of communal entrance door to cotswold green to commence September 2026 – ON HOLD
Flats 9-12
- New stainless-steel balustrades installed in addition to incumbent wooden balustrades – COMPLETED
- Re-paint of communal entrance door to cotswold green to commence September 2026 – ON HOLD
Flats 7 & 8
- Outside Stairs repair works ongoing, with more replacement step tiles, and pointing to do – CHANGE OF CONTRACTOR & REDUCED COST
- Re-paint of entrance doors to cotswold green to commence September 2026 – ON HOLD
- Re-paint of storage door outside Flat 7 to cotswold green to commence September 2026 – ON HOLD
- Re-paint of Bin Area doors to cotswold green to commence September 2026– ON HOLD
All Flats
- Soffits repaired and re-painted – Front Elevation – COMPLETED
- Soffits repaired and painted – Rear Elevation (repainting outstanding on soffit between Flats 3 & 4) – ON HOLD
- Soffit underboard replaced and repainted above Flats 9-12 entrance door – COMPLETED
- Soffits repaired and painted – Side Elevation – Flats 9-12 – COMPLETED
- Roof repairs completed – Front Elevation- COMPLETED
- Leaves and other debris removed from ceiling VELUX window in Flats 1-6 communal area- COMPLETED
Other work – ALL COMPLETED
- New Beaufield Gate sign installed on central pillar at entrance to property, with solar lighting above (permanent dim light, sensor activates 20 seconds bright light)
- New solar lighting installed in Bin Area (permanent dim light, sensor activates 20 seconds bright light)
- Drooping satellite wiring above flat 10 garden door cable tied
- Solar lights placed in rear communal gardens (permanent dim light, sensor activates 20 seconds bright light)
- Solar light installed above rear gate lock (permanent dim light, sensor activates 20 seconds bright light)
Coming soon
- Soffit painting in between Flats 3 & 4– ON HOLD
- Soffits repair and painting – Side Elevation – Flats 1-6– ON HOLD
- Repair roof tiles – Rear Elevation – awaiting quote from builders (work originally planned for 2027)– ON HOLD
- Replace coconut mats in communal entrance – Flats 1-6 and 9-12- COMPLETED
- Extensive external drains inspection, and possible deep cleaning following reports of gurgling sounds coming from some flat’s sinks/basins-APPROACHED CONTRACTORS FOR PRICING
Exploring
- Health & Safety risk with walkway to communal entrance of Flats 1-6
- There is a 2 metre gap between supporting joists causing decking to ‘bounce’
- Considering Steel replacement for wood decking, or adding additional joists to bridge the gap to incumbent decking
- New Electrician firm to review:
- Electrical infrastructure and safety certification
- Replacing external lights at rear outside garden flats (F1, F2, F7, F9, F10)
- Replace sensor light outside communal entrance to Flats 9-12 – comes on day & night
- Recommend a new external light management system to control external light timings
- Fix bollard light at entrance to property
- Unfortunately our new cleaner handed notice so we are searching for a replacement, with whom we will discuss:
- Cleaning schedule (e.g. more in winter, less in summer)– In Progress
- Deep cleaning of communal area carpets (Flats 1-6 & 9-12)– In Progress
- Repair, or replace front hand railings, and balconies on rear elevation
- Repairs will involve stripping paint to core, and undertaking rust treatment – Owners need to decide new enduring paint colour
- Apply permanent anti-slip, especially for stair rails (Flats 7 & 8)
- Get quotes for repair vs replace